Continuation of IT Modernisation Project of Department of Posts – Phase II

The Cabinet Committee on Economic Affairs on 22/11/2012 approved the proposal of Rs.4,909 crore towards IT modernisation project of the Department of Posts, covering 1.55 lakhs post offices. 

The total expenditure for the project involving Rs.4,909 crore includes both implementation phase and operation and maintenance phase for the IT infrastructure of Post Offices. The IT project of the Department is a part of the Mission Mode Project (MMP) included in the National e-Governance Plan (NEGP). 

The Department of Posts has a network of 1.55 Lakhs post offices spread across all the States and Union Territories of the country. The key objective of the India Post IT Modernisation project is modernization and computerization of all Post offices in the country including branch post offices in rural areas to create a urban-rural network spanning across the length and breadth of the country. 


The IT modernisation project is expected to give following benefits to the citizens of the country: 

• Improve customer satisfaction due to faster and more reliable delivery of services 

• Enhance visibility and transparency 

• Provide access by multiple channels to the customers e.g. post office counters, kiosks, internet, mobiles ATMs etc; 

• Ensure delivery of "citizen centric services" 


The IT modernisation project will provide a national asset and infrastructure for all users apart from the post offices including various government departments, business houses and the citizens to use the services effectively for their communication, banking, insurance and service delivery needs. The project will improve the delivery of mails, banking and insurance services rendered by the Post offices across the length and breadth of the country. 

For the purpose of implementation, the IT modernisation project has been structured into 8 segments catering to IT infrastructure such as datacentre, network, computers and peripherals, software applications which will cover all the product and services of the Department of Posts, and change management which will help in effective transformation into IT mode. The project will be implemented in all the 1.55 lakh post offices in a phased manner over a time period of 2 years, to be followed by the O&M phase over the period of contract. 

The project will be rolled out to all the post offices covering all States and Union Territories in the country a phased manner. 


Background: 

The proposal of the Department of Posts is in continuation of the proposal which was approved by the Cabinet Committee on Economic Affairs (CCEA) on 26th Aug 2010. The overall project has been segregated into eight RFPs, of which, selection of vendors have been finalized in case of 5 RFPs and LOIs have been issued. Of these 5 RFPs, in four cases the contracts have been signed with the selected bidders. In respect of two RFPs the financial bids have been opened and selection of the bidder is under process. 

Source:-PIB

Comments

Popular posts from this blog

Duties and additional duties of Postman----for information of all supervisory cadre

  DG(P) No.11-1/2010-Admn dated 18-11-2010 NO.25-20/2008-PE-I Government of India Ministry of Communications & IT Department of Posts (Establishment Division)                                                                                                        Dak Bhavan, Sansad Marg                                                                                          New Delhi                                                                                                       Dated 25.11.2008   TO              All Heads of Circles/Regions,   Subject: Additional duties for Postman/Delivery Staff.                                       On account of changes in work scenario of the Post offices brought about due to the induction of technology and primacy of business products, the duties and responsibilities of the postman have undergone a vast change. In order to incorporate these changes, the following duties are prescribed in addition to t
ENHANCEMENT OF FINANCIAL POWERS OF HSG, HSG-II AND LSG POST MASTERS ( THESE ORDERS ARE IN FORCE. NO REVISION TAKES PLACE SINCE 21 YEARS) A reference is invited to Circular No.62-8/64-CI dated 20.10.1965 delegating financial powers to HSG and LSG Postmasters to incur expenditure of a contingent nature on the following items: a) Replacing, repairing, cleaning, oiling, shifting of electric lights and fittings, fans etc. of the office in a rented building when the charge is a Government liability. b) Repairs of Department bicycles. c) Purchase of earthen pots, glass tumblers, dusters, brooms etc. d) Purchase and repairs to furniture. e) Emergent arrangements for conveyance of mails. 2. The question of enhancement of the powers were being examined in the Directorate in view of the rise in the prices and it has been decided to enhance the powers given to HSG & LSG Postmasters from Rs.30 & Rs.20/- respectively on each occasion to Rs.60/- & Rs.40/- respectively on each o
GRANT OF TA & TRANSIT (TA & TP) TO OFFICIALS TRANSFERRED ON COMPLETION OF TENURE TO THE PLACE OF THEIR CHOICE . A proposal on grant TA and transit to officials who are transferred on completion of tenure to the place of their choice was under consideration in this Directorate for sometime past.      SR-114 governs TA on transfer distinguishes between transfer for public convenience and transfer on own request.  Although transfer on completion of tenure in one office has not been specifically referred to in this rule, yet the transfer on completion of tenure is a transfer for public convenience.  On completion of tenure, the official has to be transferred out for operational reasons.  Therefore, such a transfer is mandatory, while posting to a place of choice is secondary and subject to public convenience.  In view of this posting to a place of choice after completion of full tenure may not be normally termed as a "transfer on own request" under SR-114.      It