Infosys has made changes in the EOD execution procedure. The major changes done by infosys to address EOD issues ar as follows:





1. SOLs should only run HISCOD menu ( new menu available for PO user - SU, SA, PM )


2. HSCOD, HSOLCOP and HSCOLD to be executed by CPCs in circle sets

Centralized EOD Execution:

SOL EOD execution comprises of executing HSCOD, HSOLCOP & HSCOLD menu. Please find the current DOP executing procedure and the centralized EOD execution procedure to be followed,

DOP is following current EOD execution procedure, 

 
Execution of EOD 1st Menu
HSCOD
Branch User will be executing after clearing the blocking validation
Execution of EOD 2nd Menu
HSOLCOP
Circle SPOCs will be executing for their SETs with optimal parallelization as 20 once HSCOD is completed for their SETs
Execution of EOD 3rd Menu
HSCOLD
Circle SPOCs will be executing for their SETs with optimal parallelization as 20 once HSOLCOP is completed for their SETs

This has to be changed to Centralized EOD execution procedure,


Submission of Pre EOD Menu
HISCOD
Branch User will be submitting after clearing the blocking validation
Execution of EOD 1st Menu

HSCOD
CPC User will be executing with optimal parallelization as 20 once HISCOD is submitted for their SETs
Execution of EOD 2nd Menu
HSOLCOP
Circle SPOCs will be executing for their SETs with optimal parallelization as 20 once HSCOD is completed for their SETs
Execution of EOD 3rd Menu
HSCOLD
Circle SPOCs will be executing for their SETs with optimal parallelization as 20 once HSOLCOP is completed for their SETs

During EOD execution, the overall EOD progress for the Circle to be monitored & co-ordinated by CPC team centrally.

Submission of Pre EOD Menu by Branch User:

Please find the procedure to be followed by Branch user for Submitting Pre EOD menu,

Invoke HISCOD (Initiate SOL Change Operation Date) menu

Provide the SOL ID under the field “SOL SET ID”,Hours as 0 & Minutes as 1

Submit


 SOL Level Date Change Execution by CPC:

Please find the procedure to be followed by CPC user for SOL Date Change Execution,

Invoke HSCOD (SOL Change Operation Date) menu

Provide the Circle SET ID under field “SOL SET ID”

Provide Optimal Parallelization under field “No. of Parallel SOLs”

Submit

CPC user can inquire lists of SOLs where HISCOD submitted for their Set through HSSI menu.
CPC user can inquire the HSCOD running status for their Set through HSSI menu.
The EOD Status of particular SET or for all SOLs can be monitored through HSSI menu.

Comments

Popular posts from this blog

Model representation to be submitted to Head of the office for grant of One Increment

Model representation to be submitted to Head of the office for grant of One Increment Government servants are aware that the Ministry of Finance and Railways, both have already issued orders for grant of one increment in the pre-revised pay scale to nullify the anomaly in respect of central government employees who were in receipt of pre-revised increment between February 2006 to June 2006. A model representation requesting the concerned head of Office for grant of one increment and drawl of arrears is published below for ready use. MODEL REPRESENTATION FOR GRANT OF ONE INCREMENT From : To, Sir / Madam, ·   Sub: Officers who were due to get heir annual increment between February to June during 2006 – Grant of additional increment as one time measure- Request for sanction and drawal of arrears – Reg. Kind reference is invited to the Ministry of Finance, Department of Expenditure O.M.No.10/02/2011- E.III/A dated 19th March, 2012 wherein all the centra...

Cabinet approves Implementation of the recommendations of 7th Central Pay Commission

  The Union Cabinet chaired by the Prime Minister Shri Narendra Modi has approved the implementation of the recommendations of 7 th  Central Pay Commission (CPC) on pay and pensionary benefits.   It will come into effect from 01.01.2016. In the past, the employees had to wait for 19 months for the implementation of the Commission’s recommendations at the time of 5 th  CPC, and for 32 months at the time of implementation of 6 th  CPC.  However, this time, 7 th  CPC recommendations are being implemented within 6 months from the due date. The Cabinet has also decided that arrears of pay and pensionary benefits will be paid during the current financial year (2016-17) itself, unlike in the past when parts of arrears were paid in the next financial year.  The recommendations will benefit over 1 crore employees. This includes over 47 lakh central government employees and 53 lakh pensioners, of which 14 lakh employees and 18 lakh pe...
ENHANCEMENT OF FINANCIAL POWERS OF HSG, HSG-II AND LSG POST MASTERS ( THESE ORDERS ARE IN FORCE. NO REVISION TAKES PLACE SINCE 21 YEARS) A reference is invited to Circular No.62-8/64-CI dated 20.10.1965 delegating financial powers to HSG and LSG Postmasters to incur expenditure of a contingent nature on the following items: a) Replacing, repairing, cleaning, oiling, shifting of electric lights and fittings, fans etc. of the office in a rented building when the charge is a Government liability. b) Repairs of Department bicycles. c) Purchase of earthen pots, glass tumblers, dusters, brooms etc. d) Purchase and repairs to furniture. e) Emergent arrangements for conveyance of mails. 2. The question of enhancement of the powers were being examined in the Directorate in view of the rise in the prices and it has been decided to enhance the powers given to HSG & LSG Postmasters from Rs.30 & Rs.20/- respectively on each occasion to Rs.60/- & Rs.40/- respectively on each o...