I.        The BO should have table to place the Handheld Device and for charging the device.

 II.        The electrical power connection is required to charge the Solar UPS wherever power is available. In the locations where electrical power is not available, the UPS will be charged from Solar Panel.

  III.        The locations where electrical power connection is there, it should have proper earthing and with one or two plug points along with on/off switch.

   IV.        The above site preparation is to be done before the roll out starts for the particular Division.

    V.        The data on BO such as the name of the BPMcontact detailsaddress of the BO with land marks etc. may be updated and kept ready.

   VI.        The availability of the network connectivity (Vodafone/ BSNL / Airtel etc.)at the BO location may also accessed and the best signal available in the BO may be identified and kept in order to facilitate the Vendor with details to drive best out of the project. If the network signal is not available, we have to identify as Off-line BO.

 VII.        Similarly identification of the BOs where the solar UPS is not required due to installation problems of the solar panel or good power availability for more than 6 hours daily, has to be also done.  To view the format for collection of desired information in respect of Branch Post Offices please CLICK HERE

The complete information in respect of all BOs is to be uploaded to the specific webpage domain name (to be circulated shortly) on the India Post website by 30-12-2014.


Source : Department of Posts (RB Division) Letter No.01-07/2014-RB dated 27-11-2014. 

Comments

Popular posts from this blog

Model representation to be submitted to Head of the office for grant of One Increment

Model representation to be submitted to Head of the office for grant of One Increment Government servants are aware that the Ministry of Finance and Railways, both have already issued orders for grant of one increment in the pre-revised pay scale to nullify the anomaly in respect of central government employees who were in receipt of pre-revised increment between February 2006 to June 2006. A model representation requesting the concerned head of Office for grant of one increment and drawl of arrears is published below for ready use. MODEL REPRESENTATION FOR GRANT OF ONE INCREMENT From : To, Sir / Madam, ·   Sub: Officers who were due to get heir annual increment between February to June during 2006 – Grant of additional increment as one time measure- Request for sanction and drawal of arrears – Reg. Kind reference is invited to the Ministry of Finance, Department of Expenditure O.M.No.10/02/2011- E.III/A dated 19th March, 2012 wherein all the centra...

Cabinet approves Implementation of the recommendations of 7th Central Pay Commission

  The Union Cabinet chaired by the Prime Minister Shri Narendra Modi has approved the implementation of the recommendations of 7 th  Central Pay Commission (CPC) on pay and pensionary benefits.   It will come into effect from 01.01.2016. In the past, the employees had to wait for 19 months for the implementation of the Commission’s recommendations at the time of 5 th  CPC, and for 32 months at the time of implementation of 6 th  CPC.  However, this time, 7 th  CPC recommendations are being implemented within 6 months from the due date. The Cabinet has also decided that arrears of pay and pensionary benefits will be paid during the current financial year (2016-17) itself, unlike in the past when parts of arrears were paid in the next financial year.  The recommendations will benefit over 1 crore employees. This includes over 47 lakh central government employees and 53 lakh pensioners, of which 14 lakh employees and 18 lakh pe...
ENHANCEMENT OF FINANCIAL POWERS OF HSG, HSG-II AND LSG POST MASTERS ( THESE ORDERS ARE IN FORCE. NO REVISION TAKES PLACE SINCE 21 YEARS) A reference is invited to Circular No.62-8/64-CI dated 20.10.1965 delegating financial powers to HSG and LSG Postmasters to incur expenditure of a contingent nature on the following items: a) Replacing, repairing, cleaning, oiling, shifting of electric lights and fittings, fans etc. of the office in a rented building when the charge is a Government liability. b) Repairs of Department bicycles. c) Purchase of earthen pots, glass tumblers, dusters, brooms etc. d) Purchase and repairs to furniture. e) Emergent arrangements for conveyance of mails. 2. The question of enhancement of the powers were being examined in the Directorate in view of the rise in the prices and it has been decided to enhance the powers given to HSG & LSG Postmasters from Rs.30 & Rs.20/- respectively on each occasion to Rs.60/- & Rs.40/- respectively on each o...